Whittier Safe Routes to School Phase 2

This is a Safe Routes to School project focused on Whittier Elementary School. The City will be improving traffic safety to make walking and biking to school easier.

Key information

Dates

2023 – 2027

Location

W. 26th, 27th, and 28th streets between Blaisdell Avenue and Lyndale Avenue S. Intersection of E. 26th Street at Stevens Avenue

Whittier

Project overview

This project will add safety improvements near Whittier Elementary School. The project area includes W. 26th, 27th, and 28th streets between Blaisdell Avenue and Lyndale Avenue S. The intersection of E. 26th Street at Stevens Avenue will also be improved.

Project goals

  • Improve comfort and safety for students walking and biking to school
  • Create calmer streets for users of all ages and abilities
  • Improve access to Whittier Elementary School
  • Address traffic safety needs at intersections

Phase 1

Phase 1 of this project added improvements at these intersections:

  • W 26th St and Grand Ave
  • W 27th St and Blaisdell Ave

Learn more about Phase 1

View the interactive map

Construction updates

The project construction includes

  • Bituminous and concrete surfacing
  • Americans with Disabilities Act (ADA) compliant ramps
  • Intersection crossing improvements
  • Curb extensions
  • Revise traffic signal systems
  • Improve underground utility systems
  • Signage and new pavement markings
  • Buffer and separate bicycle lanes

2026 Construction

The safe routes to school construction project commenced in the week of June 22, 2026.

Four construction stages were completed in 2026.

Minor tasks will continue to be worked on until they are fully completed by the end of this year.

2027 Construction

Mill and overlay will take place on W. 26th and 28th Streets between Lyndale and Nicollet Ave.

Construction of stage five will follow the mill and overlay. That includes concrete median and bike buffer work for W. 26th and 28th Streets.

Installation of permanent signing and pavement markings will be performed in 2027.

Traffic Impacts

  • 26th and 28th Streets are currently fully open to Traffic.
  • Temporary bike detour is still in place on the south side on 28th Street.

Bi-weekly stakeholder meeting

No stakeholder meeting will be held for Whittier SRTS Phase 2 in 2027.

Sign up for alerts for important upcoming project construction information

Thank you for your support!

Community engagement

Neighborhood pre-construction meeting - June 11, 2026

This meeting covered an overview of the project. We also went over important construction information. 

Whittier Neighborhood Day

Project staff attended Whittier Neighborhood Day on May 3, 2025.

Fall 2024 engagement

There were two ways the public provided feedback on this project:

  • Completed a survey
  • Shared their experiences on an online feedback map
Whittier Safe Routes to School Phase 2 complete 2 - tile
A protected bikeway and sidewalk next to a street.

Project phase

This project is in progress. 

Input

Design

In Progress

Complete

Safe Routes to School projects

For more information on other Safe Routes to School (SRTS) safety improvements, visit the Safe Routes to School program page.

Contact us

Nguyen Nguyen

Construction Engineer 
Public Works

Phone

612-875-8727

Noah Morrick

Chief Field Inspector

Public Works

Phone

612-394-8900