Green Central Safe Routes to School

The City will make walking and bicycle safety updates near Green Central Elementary School.

Key information

Dates

2021-2024

Location

E 34th St (Clinton Ave – 10th Ave), 10th Ave S (E 34th St – E 28th St), and 11th Ave S (E 34th St – E 28th St)

Central Midtown Phillips Powderhorn Park

Project overview

Project details

The Green Central Safe Routes to School (SRTS) project will update 1.3 miles of walking and bicycle paths on East 34th Street and 10th/11th Avenues South.

The updates will help people of all ages and abilities.

This project will build a safe connection to Green Central Elementary School, other bikeways, parks, and important destinations in the area.

 

View interactive map

Safe Routes to School projects

For more information on other Safe Routes to School (SRTS) safety improvements, visit the Safe Routes to School program page.

Project updates

2024 Construction

This SRTS construction anticipates start date in mid-July, 2024.

What is happening?

  • Stage 1 – Improvement E 34th St begins July 16.
  • Removals, utility work, and paving will take place on E 34th

What to expect!

  • Roadwork and utility-work involve use of heavy equipment that will increase noise, vibration, and dust in work areas.
  • E 34th St becomes one-way street from 3rd Ave S to Chicago Ave during construction.
  • Partial closures are on E 34th St and 10th Ave S.
  • Detour routes at hard closure of E 34th St & 10th Ave S will be E Elliot Ave, E 35th St, and 10th Ave S.
  • Local access will be maintained during construction.
  • Temporary pedestrian accessible routes will vary by block depending on construction activity.

2024 Capital Project 

The proposed concept layout for E 34th Street and 10th Avenue S are now available. Public Works will present the project to the Public Works and Infrastructure (PWI) Committee. The PWI Committee is apart of the Minneapolis City Council who will review it. The Public Works team will seek approval for the proposed layout on Thursday, June 8th, 2023, at 1:30 PM.

See the proposed concept layout

Note: This layout may take additional time to load due to large file size.

2023 Demonstration project 

A demonstration project was installed along East 34th Street from Clinton Avenue to Park Avenue. The project aims to try out changes using temporary materials. This will help plan for the permanent improvements in the 2024 Green Central Safe Routes to School project. The project will make walking and bicycling to school easier, safer, and more enjoyable for students. This demonstration project features:

  • Crossing enhancements, including marked crosswalks at Clinton Ave @ E 34th St.
  • Curb extensions at Clinton Ave @ E 34th St to help narrow the crossing distance for children walking to school.
  • An in-street bollard protected two-way bikeway from Clinton Ave to Park Ave along the south side of E 34th St.
  • There will still be access to all driveways and alleys on E 34th St.
  • The demonstration project was installed on April 27, 2023. The project will remain in place until construction begins for permanent improvements in the Spring of 2024.

See the demonstration project

Survey

See the 2023 Demonstration project summary & survey result summary

Bi-weekly stakeholder meeting

Join us at the Green Central SRTS - Bi-weekly stakeholder meeting to get an overview of the upcoming construction work. We will hold the meetings virtually using Microsoft Teams. Meetings will occur every other Thursday starting July 25th, 2024 and run throughout reconstruction.

  • Every other Thursday
    9:00 - 10:00 a.m.
    via Microsoft Teams
    (The meeting will adjourn after 10 minutes with nonappearance)

  • Meeting ID: 228 101 592 789   
  • Passcode: y59jmV
  • Call In number: +1 612-276-6670   
  • Phone Conference ID: 224 652 561# 

Join the Green Central SRTS - Bi-weekly stakeholder meeting

Accessing the stakeholder meeting via your mobile device may require downloading of the Microsoft Teams app to your mobile device.

 

Help with Microsoft Teams

Anyone can join a Microsoft Teams web meeting. A free software download may be required. The type of download may vary based on how you join the meeting (computer, android device, apple device).

Learn more about Microsoft Teams

Past project meetings

Green Central SRTS Pre-construction stakeholder meeting - July 11, 2024

  • A virtual pre-construction meeting was held to provide an overview of project construction work and answer project questions.

Watch the project Pre-construction presentation

Provide feedback on the corridors

The City has created an interactive map that you can use to provide feedback on the project.

Project phase

This project is in the in progress phase.

Input

Design

In Progress

Complete

Tree lined street with parked cars.
11th Ave
Tree lined street with parked cars.
34th St
Tree lined street with large buildings in background.
10th Ave

Contact us

Nguyen Nguyen

Construction Engineer 
Public Works

Phone

612-875-8727

Iskandar Umar

Chief Field Inspector
Public Works

Phone

612-946-1526 (cell)

612-673-3204 (office)