Hennepin Ave S and Lake St connectivity improvements
Dates
2026 – 2028
Location
Hennepin Ave S between 31st St and Lake St. Lake St between Humboldt Ave S and Hennepin Ave S East Bde Maka Ska East Isles Lowry Hill East South UptownProject overview
This project will make improvements for people walking, biking, taking transit and driving. Work will take place in two phases. Interim changes will happen on Hennepin Ave in fall 2026. Permanent improvements are planned for Hennepin Ave and Lake St in 2028.
Permanent improvement project goals (construction 2028):
- Maintain plenty of space for people walking and rolling.
- Upgrade the existing bike lanes to a two-way protected bikeway on Hennepin Ave S.
- Install a new protected bikeway on Lake St.
- Provide space for curbside uses on Hennepin Ave S. These may include space for loading and unloading and short-term metered parking.
Interim improvement project goals (construction 2026):
- Make things clearer and easier to expect for everyone before the planned changes in 2028.
- Incorporate space for curbside uses on Hennepin Ave S.
- These may include space for loading and unloading or metered parking.
Project resources
Upcoming engagement
Hennepin Ave S & Lake St Open House - #1
Learn about the Hennepin Ave S & Lake St Connectivity Improvements Project. We’ll share ideas for improving safety. Join us and share your thoughts about the project.
Date
Wednesday, September 23, 2026
Time
6:00 - 7:30 p.m.
Location
Walker Library – Hennepin County Library
(Bde Maka Ska room)
View the location in Google Maps
Details
At this event, you can:
- Learn more about interim changes and permanent project
- Share feedback
Project milestones
Planning and engagement phases
Interim improvements installed
Permanent improvements planning and engagement
Permanent improvements concept finalized
Permanent improvements detailed design
Anticipated construction of permanent improvements
Sign up for project updates
Sign up to get alerts about this project. You'll need to provide your email address.
Project phase
This project is in the input phase.
Input
Design
In Progress
Complete
Contact us
Kelsey Fogt
Senior Transportation Planner
Public Works
Phone
Address
Public Service Building
505 Fourth Ave. S., Room 410
Minneapolis, MN 55415