Hennepin Ave. S. reconstruction

The City reconstructed Hennepin Ave. S. between W. Lake St. and Douglas Ave.

Key information

Dates

2018 - 2025

Location

Hennepin Ave. S. between Lake St. W. and Douglas Ave.

East Isles Lowry Hill Lowry Hill East

Project overview

The City reconstructed Hennepin Ave. between W. Lake St. and Douglas Ave. Construction was  phased over 2-years. Phase 1, from Lake St W to 26th St, was completed in 2024. Phase 2 was substantially completed from 26th St to Douglas Ave occurring in 2025.

The project updated Hennepin Avenue to meet the public’s current and future needs. The new, multimodal design improves space for people to: walk, ride transit, bike, and drive. The layout also provides space for enhanced stations of the future METRO E Line.

Preview the specific location for this project on our interactive map.

View interactive map

Sign up for weekly email updates

Construction updates

Latest project news

  • Hennepin Ave. is Open!
  • Major construction activities are substantially complete.
  • The roadway is open to 2-way traffic, bike lanes and sidewalks are open.
  • Remaining work will consist of Sanitary Sewer lining and punch list items will be taking place over the next month or so.
  • The Sewer lining was completed fall 2025.

What to expect

Bi-weekly stakeholder meeting

The Hennepin Ave S stakeholder meetings have now concluded. Thank you for your participation and support of this Public Works project.



Past meetings

Public meeting #8 - Construction stakeholder meeting

We held a virtual public meeting on March 12, 2024 to provide construction updates, discuss construction impacts, and answer questions and concerns.

Public meeting #7 - Construction stakeholder meeting

We held a virtual public meeting on February 22, 2024 to provide construction updates, discuss construction impacts, and answer questions and concerns.

Public meeting #6 - Construction stakeholder meeting

We held a virtual public meeting on October 19, 2023 to provide construction updates, discuss construction impacts, and answer questions and concerns.

Public meeting #5 - Pre-construction informational meeting

We held a virtual public meeting on August 15, 2023 to share an overview of the construction schedule, discuss construction impacts, and answer questions and concerns.

Hennepin Ave S public meetings – Pre-2023

Project update - November 6, 2025

We send out regular email updates for the Hennepin Ave S reconstruction project. Sign up for updates below.

Project phase

The project is currently in the in progress phase.

Input

Design

In Progress

Complete

Uptown theater at Hennepin Ave. South and W. Lake St.
Uptown Theatre at Hennepin and Lake
Bus on Hennepin Ave. South
Bus on Hennepin Ave. S.

Contact us

Adam Hayow

Project Engineer

Public Works

Phone

612-673-2172