2nd St. resurfacing and corridor improvements
Dates
Installation in 2023
Location
2nd Street S. from 2nd Avenue S. to 13th Avenue S. in downtown Minneapolis Downtown East Downtown WestProject overview
As part of this work, we're considering changes to improve safety for all people, with a focus on:
• Encouraging safer travel speeds
• Improving safety for people walking
• Upgrading the street corners to include accessible curb ramps
• Creating an all ages and abilities bicycle route
Resurfacing work
We'll replace the top layer of pavement as part of an ongoing maintenance program. This will extend the life of the street between larger reconstructions projects. The new pavement should last at least 10 years.
Safety work
We'll also look at changes to the existing street configuration to improve safety.
This includes:
• Installing an accessible curb ramp at corners where there is a need
• Narrowing the street to better manage vehicle speeds by creating a two-way bikeway on one side of the street
• Making it safer to walk across the street with concrete medians at priority locations
Project goals
• Make it safer to walk along and across the corridor
• Create an all ages and abilities bicycle facility
• Keep traffic moving at an acceptable level
• Allow access for residents and visitors
Traffic impacts
Construction is underway and is anticipated to conclude by the end of 2023. During the first phase of work, there will be some parking restrictions but no long-term road closures. We will maintain access for residents and visitors.
Community engagement
Upcoming meetings
We will hold at least three public meetings to provide updates on the project. You can also sign up for email updates below.
- August 16, 6 – 7 p.m. The Depot, 225 3rd Ave S, Minneapolis
- September 20, 6 – 7 p.m. The Depot, 225 3rd Ave S, Minneapolis
- October 18, 6 – 7 p.m. The Depot, 225 3rd Ave S, Minneapolis Cancelled
There will be a survey in late October, which will be your opportunity to provide input on the project and process. A link to the survey will be posted here, stay tuned.
Meetings
We welcome community feedback and input. To-date we have done two rounds of community engagement to:
- Identify priorities.
- Review potential improvement options
- Develop a design concept for the project
See the community engagement report
- This report is a summary of the completed community engagement activities.
Past community meetings
- On March 21st, 2023, an open house held to present the recommended design for the project.
- On April 12th, 2023 an information meeting was held to present the overview of the project and the special assessment process.
Contact us with your questions and comments at any time
Project timeline
January 2022 – January 2023
Community engagement phase 1 and concept design (Spring 2022)
Community engagement phase 2 and concept design (Fall 2022/winter 2023)
February – March 2023
Detailed engineering
Summer 2023
Phase 3 timeline
- Pedestrian ramp work: July 24 – August 21, 2023
- Select curb and gutter work: July 24 – August 21, 2023 (tentative)
- Pavement repairs: August 21 – September 25 (tentative)
- Concrete safety improvement work: September 25 – November 6 (tentative)
Project phase
This project is complete.
Input
Design
In Progress
Complete
Project update - November 1, 2023
Sign up for project updates
Sign up to get alerts about this project. You'll need to provide your email address.