Project overview

 

A few years ago, the City rebuilt Johnson St NE from 18th Ave NE to Lowry Ave NE. The project:

  • Fixed old roads and pipes
  • Made it safer for people walking or rolling
  • Added a new trail for pedestrians and bikes

It also included green infrastructure. That is infrastructure that mimics or uses natural systems to improve resilience to climate impacts. This often results in environmental, economic, and social co-benefits.

In the fall and early winter of 2024, we worked with the community to select the plantings they wanted to see along the boulevard.

In Spring 2025, a contractor will restore the boulevards with various native plantings and grasses. The contractor will care for the plantings through the fall. Once the plantings are well established, the boulevards will be returned to the property owners for on-going care. The contractor will provide property owners with guidance on caring for their boulevard.

Project updates

 

19th Avenue to Lowry Avenue

  • The City’s contractor will begin site preparation on Monday, June 16th.
  • They will start on 19th Avenue and work north to Lowry, completing one side of the street at a time.
  • Site preparation will be completed (on both sides) by the end of the day on Friday, June 20th.
  • During the work, Johnson St will remain open to traffic. The sidewalk/bike trail will be closed on the side of the street where the work is occurring. Please use the sidewalk/bike trail on the other side of the street travel around the work area.
  • Seeding of Bee Lawn will also be completed at the same time.
  • Planting plugs and placing sod will occur the week of June 23rd.
  • After seeding/plants/sod are installed, the Contractor will maintain (water, and repairing bare spots) until November 1st, 2025.

18th Avenue to 19th Avenue

  • The City’s contractor will begin site preparation on Monday, June 30th.
  • Site preparation will be completed (on both sides) by the end of the day on Friday, July 11th.
  • During the work, Johnson St will remain open to traffic. The sidewalk/bike trail will be closed on the side of the street where the work is occurring. Please use the sidewalk/bike trail on the other side of the street travel around the work area.
  • Seeding of Bee Lawn, and planting plugs, will also occur during this time.
  • After seeding/plants are installed, the Contractor will maintain (watering, and repairing bare spots) until November 1st, 2025.

Project phase

This project is in progress.

Input

Design

In Progress

Complete

Johnson Ave NE street view

Contact us

Michael Richie

Construction Engineer

Public Works

Phone

612-673-3628

Allison Bell

Professional Engineer

Public Works