Columbus and Park Ave alley reconstruction
The City will fix the alley between Columbus Ave S, Park Ave S, 45th St E, and 46th St E to help with drainage.
Dates
Summer - Fall 2025
Location
The alley between Columbus Ave S, Park Ave S, 45th St E, and 46th St E. Downtown WestProject overview
This alley was originally constructed in 1937. There has been soil settlement resulting in low spots that do not drain properly. The alley will be reconstructed. The existing concrete pavement and base will be removed. A new base will be placed and a new concrete alley will be poured.
Traffic impacts
The alley will be closed during construction.
Community engagement
Pre-public hearing meeting
Project held a meeting on May 1, 2025. This was an informational meeting ahead of the public hearing.
Project phase
This project is in the input phase.