42nd St E alley storm sewer improvements

The project will replace failing and undersized storm sewer near 42nd St E between Chicago Ave and 14th Ave S.

Key information

Dates

2026

Location

Alleys on the north side of 42nd St E between Chicago Ave and 14th Ave S

Bancroft

Project overview

City crews will replace 950 feet of sewer and the related structures. They will also improve the sewer layout in 42nd St E & Elliot Ave and 42nd St E & 13th Ave S. 

Two new concrete alleys will also be built following the sewer work. 

View the interactive map

An online informational meeting will take place on Thursday, March 5th at 6:00 PM CST.

Join the Teams meeting

Traffic impacts

Expect the following temporary traffic impacts:

  • Detours
  • Lane restrictions
  • Intersection reductions
  • Parking restrictions
  • Revised pedestrian and bicycle routes

Residents, businesses and visitors may experience:

  • Noise
  • Vibration
  • Dust in work areas

Alleys will close during concrete pouring.

Project phase

This project is in the design phase.

Input

Design

In Progress

Complete