19th Avenue S

Final project layout (pdf)


 

Project Type

On-street bike lanes and shared lane markings (aka sharrows)

Project Limits

19th Avenue S

Construction Start Date

2011

Contact Information

Shaun Murphy, (612) 333-2450 or shaun.murphy@minneapolismn.gov. Feedback can also be entered using our online form.

Project Details

Lane changes will include bike lanes in each direction on every block of the project, except for the southbound direction between 2nd Street S and Washington Avenue S. In general two of the four travel lanes will be removed between 2nd Street S and Riverside Avenue. Several turn lanes and painted medians will be added in the 2nd to Riverside section.

Striping will be in permanent tape between Riverside Avenue and Washington Avenue. A layer of seal coating will be laid over the roadway surface, and permanent tape will be laid into this layer. The remainder of the project will be milled and overlaid as part of the 35W Detour Route Rehabilitation Project, and striping will be in paint.

No parking changes will take place.

Bike racks will be installed.

Project Updates

August 16, 2010

The final striping and signing plans have been approved by City and MnDOT staff and final approval has come from FHWA. In order to coordinate this project with the 35W Detour Route Rehabilitation Project which will take place in 2011, the entire project has been delayed until next year.

June 5, 2009

On Wednesday, June 10th, Public Works will host a public meeting striping and signing changes (pdf) and a project summary (pdf) are available for review.

Other Information

This project is part of the larger Bicycle Operations project, and was funded by the federal Non-Motorized Transportation Pilot Program.

Last updated Mar 16, 2012