Projects In Progress

Not Funded

Related Links

Contact Us

Camden Bridge Rehabilitation Project

This interactive graphic requires Adobe Flash v.8 or higher.
Get the free Flash Player from Adobe.com.


If you are unable to update the Flash plug-in on your web browser, or are seeing this message instead of a chart graphic, we apologize. Please use the data view or download the data using the links above.

The City of Minneapolis is not a primary recipient on this project. No Federal Report XML is submitted for this project.

Dollars Awarded

$9,565,904

Project Status

Fully completed

Project Description

$10,000,000 ARRA award for the rehabilitation of the Camden Bridge Project. Award is for construction only and does not cover design and engineering oversight activities. Construction activies include the removal and replacement of the bridge deck, vehicle crash barrior, decorative railing and lighting. The pin and hanger connections to the superstructure will be replaced and upgraded as part of this project as well. In addition, the bridge will be repainted. Based on accepted bid the approved ARRA funds are capped at $ 9,539,618. The final amount was $9,565,903.62.

Funding Program

Supplemental Discretionary Grants for National Surface Transporation System

Responsibility for Implementation

Public Works

Funding Agency

US Department of Transportation

Dollars Leveraged

$9,565,904

Dollars Leveraged Description

$10,000,000 for actual construction costs capped at $9,539,618. Project prep work is ongoing. Construction scheduled to begin April 5th with the bridge closure on April 12, 2010.

Dollars Requested

$9,565,904

Projected Jobs Created

93

Award Type

Grant

Sub-recipient Names

Minneapolis, City of

Vendor Names

Lunda Construction Company

Recovery Funds Spent to Date

$9,565,904