New truss span in place for St. Anthony Parkway Bridge

May 11, 2017 (MINNEAPOLIS) Crews reached a major milestone this week for the new St. Anthony Parkway Bridge by moving a new truss span into place over the Burlington Northern Santa Fe (BNSF) rail yard in northeast Minneapolis.

It took about 10 hours Tuesday and Wednesday to move the approximately 305 foot long, 1.6 million pound truss into position. The St. Anthony Parkway Bridge is a three-span bridge over the BNSF Northtown rail yard that will accommodate the St. Anthony Parkway, bicyclists and pedestrians once complete. The bridge is expected to open early fall 2017. 

Future work on the bridge includes lowering the truss into final position, which is scheduled for the end of next week, installing steel girders for the remaining new spans and a deck placement.

The new bridge replaces a five-span bridge built in 1925. It is part of the Grand Rounds National Scenic Byway. The cost of the project is $31.6 million and includes City, federal and state funding and a contribution from BNSF Railway.

For additional information about the project and a live webcam, go to stapbridge.com. For time-lapse video and additional photos of the new truss span, go to news.minneapolismn.gov.

 

 

 

Published May 11, 2017

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

 

facebook25x25 twitter25x25 youtube25x25 Minneapolis311icon logo tv 14 footer icon image linkedin_32x32




mpls-logo-white120