1.   Burroughs N Area and Dupont Ave S Street Resurfacing Project:
a)   Approve Resolution designating the location and improvements proposed to be made in the project;
b)   Receive the cost estimate of $1,400,222, the list of benefited properties, and direct the City Engineer to prepare proposed special assessments against the benefited properties; and
c)   Set a public hearing to be held on April 1, 2014.
Staff Report:  Burroughs and Dupont Resurfacing RCABurroughs and Dupont Map
Action Taken:  Approved.
 
2.   Johnson St NE, 10th and 11th Aves SE Street Resurfacing Project:
a)   Approve Resolution designating the location and improvements proposed to be made in the project;
b)   Receive the cost estimate of $202,864, the list of benefited properties, and direct the City Engineer to prepare proposed special assessments against the benefited properties; and
c)   Set a public hearing to be held on April 1, 2014.
Staff Report:  Johnson, 10th, 11th Resurfacing RCAJohnson, 10th, 11th Map
Action Taken:  Approved.
 
3.   Franklin Ave Bridge Rehabilitation:
Approve the project layout for the rehabilitation of the historic Cappelen Memorial Bridge (Franklin Ave over the Mississippi River) and full bridge closure for up to 4 months.
Staff Report:  Franklin Ave Bridge RCAFranklin Bridge Layout

Action Taken:  Approved.  Public Works staff directed to work with Hennepin County staff and the Minneapolis Bicycle Advisory Committee to develop a safe and convenient connection for eastbound bicyclists on Franklin Ave to the bike lanes on northbound 27th Ave SE.

 
4.   Toltz King Duvall Anderson (TKDA) Contract Amendment:
a)   Extend expiration date of TKDA Consultant Pool Scope 9 to April 30, 2014 for design and construction management services for electric car charging stations at multiple parking ramps;
b)   Extend expiration date of TKDA Consultant Pool Scope 10 to December 31, 2014 for design and construction management services for the replacement of air handler units at the 11th & Marquette Ramp Skyways; and
c)   Extend expiration date of TKDA Consultant Pool Scope 11 to December 31, 2014 for design and construction management services for the ABC Ramp Building Automation Controller Replacement Project.
(Refer to W&M)
Staff Report:  TKDA Contract Amendment RCA
Action Taken:  Approved.
 
5.   2014 Downtown Minneapolis TMO Grant Agreements:
a)   Authorize execution of a Metropolitan Council Pass-Through Grant Agreement to provide up to $407,873 in federal grant funding for Transportation Demand Management (TDM) projects for the period of January 1, 2014 through December 31, 2014;
b)   Authorize execution of an extension to the City Agreement with the Downtown Minneapolis Transportation Management Organization (TMO) to perform specific work outlined in the Met Council contract providing for the federal grant funding; and
c)   Approve increasing the appropriation and revenue in Traffic Capital Grant Fund by $407,873.
(Refer to W&M)
Staff Report:  TMO Grant Agreements RCA
Action Taken:  Approved.
 
6.   Parking Control and Security Automation Project - Federal Courthouse Ramp:
Approve increase to the contract with Harstad Company, Inc. by $24,431.73 to allow for change order items associated with the Parking Control and Security Automation Project at the Federal Courthouse Ramp.
(Refer to W&M)
Staff Report:  Federal Courthouse Ramp RCA
Action Taken:  Approved.
 
7.   Government Center Ramp Expansion Joint Project:
Approve increase to the contract with A&M Construction by $2,452.81 to allow for change order items associated with the Government Center Ramp Expansion Joint Project.
(Refer to W&M)
Staff Report:  Government Center Ramp Project RCA
Action Taken:  Approved.
 
8.   Bids:
a)   OP7886, Accept low bid of Berwald Roofing Company, Inc., for an estimated expenditure of $53,793, for the Government Center Parking Ramp Roof Replacement Project; and
b)   OP 7891, Accept low bid of Global Specialty Contractors, Inc., for an estimated expenditure of $393,630.16, for the Fridley Softening Plant Basement Rehabilitation Project.
(Refer to W&M)
Staff Report: Bid 7886Bid 7891
Action Taken:  Approved.
 
Discussion
 
9.   Washington Ave Reconstruction Project:
      a) Approve resolution approving Hennepin County Transportation Department’s Layout 3 for Washington Ave Reconstruction from Hennepin Ave to 5th Ave S, and the Concept Plan for Washington Ave from 5th Ave S to I-35W dated January 30, 2014; and
      b) Approve resolution supporting a formal request submitted by Hennepin County Transportation Department for a variance from Minnesota State Aid Rules for travel lane width for the full length of the Washington Ave Reconstruction Project.
      Staff Report:  Washington Ave Reconstruction RCAWashington Ave LayoutCounty PowerPoint;  Resolutions 

Action Taken:  Approved.  Public Works staff directed to work with Hennepin County staff and the Minneapolis Pedestrian Advisory Committee and Bicycle Advisory Committee on detailed designs for the Washington Ave bicycle and pedestrian space including, but not limited to:

·        Interactions between protected bikeway and bus stops

·        Intersection safety improvements including striping, signalization and signage

·        Green space elements

 
10.  Bus Stop Shelter Franchise Agreement and Future Direction:
       Receive and file status update on Bus Stop Shelter Franchise, following presentation.
       Staff Reports: Bus Stop Shelter Franchise RCA; Bus Shelter Photos; Maintenance Guidelines; Advertising Policy
       Action Taken:  Received and filed.
 
 
Upcoming Public Hearing
February 25, 2014 - 51st Ave N Street Resurfacing Project
 
 
Notice: A portion of this meeting may be closed to the public pursuant to MN Statutes Section 13D.03 or 13D.05
 
Next Committee Meeting: February 25, 2014
Committee actions will be referred to the next Council Meeting: February 21, 2014
 
Committee Coordinator email: Councilcommitteecoordinators@minneapolismn.gov
 
Attention: If you need this material in an alternative format, please call (612) 673-3737 or email NCR@minneapolismn.gov. Deaf and hard-of-hearing persons may use a relay service to call 311 agents at (612) 673-3000. TTY users may call (612) 673-2157 or (612) 673-2626.
Attention: If you have any questions regarding this material, please call 311 or (612) 673-2046. Hmong – Ceeb toom. Yog koj xav tau kev pab txhais cov xov no rau koy dawb, hu 612.673.2800; Spanish – Atención. Si desea recibir asistencia gratuita para traducir esta información, llama 612.673.2700; Somali – Ogow. Haddii aad dooneyso in lagaa kaalmeeyo tarjamadda macluumaadkani oo lacag la’ aan wac 612.673.3500.

The City of Minneapolis invites and encourages participation by every resident to each program, service and event within our city. Should you require an accommodation in order for you to fully participate, or should you require this document in a different format, please let us know by contacting 311 or (612) 673-3000 at least 5 days prior to the meeting

Last updated Feb 11, 2014