North Loop Paving Project

 

Sign up for email updates for North Loop Paving & Pedestrian Enhancements:

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.

 

 

 NLPaving-Map

Project Status

CIP Status Stage 1: Planning

Project Details

Project Description:
The proposed project will reconstruct portions of 3rd St N, 5th Ave N, 7th Ave N, 8th Ave N and 9th Ave N adding up to approximately 0.8 miles of street within the North Loop neighborhood. The project is a reconstruction project involving the entire right-of-way and will include new sidewalks, ramps, pavement, curb and gutter, and utility improvements. The project will also include signal improvements, new signage, and new pavement markings, as needed.

Project Location:
3rd St N (5th Ave N - 10th Ave N), 5th Ave N (5th St N - Washington Ave N), 7th Ave N (4th St N - Washington Ave N), 8th Ave N (3rd St N - Washington Ave N), 9th Ave N (3rd St N - Washington Ave N)

Project Map


Construction Date:
This project is scheduled to be completed in 2019.

Construction Duration:
TBD.

 

Meetings

The City of Minneapolis Department of Public Works will be holding a series of public meetings to gather feedback regarding the proposed project. The first two public meetings will be held at the dates below, with a third final public meeting scheduled tentatively for November 2017.
 

Public Meeting #1, Introductory Open House:

Minneapolis Central Library, Doty Board Room-N280
300 Nicollet Mall, Minneapolis, MN 55401
Monday, July 24th, 2017 
Open House Hours, 5:30 p.m. – 7:00 p.m.

 

Public Meeting #2, Preliminary Concepts Open House:

Minneapolis Central Library, Doty Board Room-N280
300 Nicollet Mall, Minneapolis, MN 55401
Tuesday, August 29th, 2017 

Open House Hours, 5:30 p.m. - 7:00 p.m.

 

Public Meeting #3, Final Recommended Concept:

 Expected in late fall 2017. Time, date and location to be determined.

 

 Existing Site Photos:
North Loop -1     North Loop -2     North Loop 3

Schedule

Planning& Public Engagement:
Community engagement will take place in the 3rd and 4th quarter 2017. More details to come.

Engineering Design:
Engineering/Final Design will take place in 2018

Construction:
Construction is scheduled for 2019
 


 

Project Updates

7/11/17 Meeting notifications for the upcoming open houses have been sent to property addresses in the area.
 

Project Contacts

Forrest Hardy, Project Planner, forrest.hardy@minneapolismn.gov     Adam Hayow, Project Engineer, Adam.Hayow@minneapolismn.gov

 

 

 

 

 

 See also, related 2019 project: North Loop Pedestrian Improvements 

Last updated Jul 11, 2017

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

 

facebook25x25 twitter25x25 youtube25x25 Minneapolis311icon logo tv 14 footer icon image linkedin_32x32




mpls-logo-white120