34th Avenue South Street Reconstruction

The City of Minneapolis proposes to reconstruct 34th Avenue South between East Minnehaha Parkway and 58th Street East. The proposed project is scheduled to occur over the course of the 2019 and 2020 construction seasons and will consist of improvements to the roadway, sidewalk and utilities. City staff is currently in the preconstruction stage for the project.

34th Ave S from 50th St to 58th St will be completed in 2019; 50th St to Minnehaha Pkwy is planned for 2020.

34th St Ave S 

Project Status

 CIP Status Stage 4: Construction

Project Details

Project Type

This project encompasses the entire right-of-way and include full removal of the existing street, subgrade correction, new pavement, curb and gutter, driveways, sidewalk as needed, streetscape elements as needed, utility work as needed, pavement markings, signals, and signage.

Project Limits

The 34th Ave South project is located in south Minneapolis from East Minnehaha Parkway to 58th Street East.

Construction Timeline

34th Ave S Timeline Graphic Revised

Photos

34th Ave S Picure 1

As shown in the photos above, this segment of 34th Ave S has pavement, sidewalks, and streetscape elements in need of repair.

 34th Ave S Construction Photo 1 4-18-19

Construction on 34th Ave S began in April of 2019.

Project Meetings

Community Meeting #1

Nokomis East Neighborhood

November 28, 2016 – 6:00 p.m.
4313 54th Street East
Minneapolis, MN 55417
Meeting Presentation
Project Fact Sheet 

Community Meeting #2

Nokomis East Neighborhood
January 25, 2017 – 6:00 p.m.
Lake Nokomis Lutheran Church
5011 31st Avenue South
Minneapolis, MN 55417
Meeting Presentation 

Community Meeting #3

Nokomis East Neighborhood
January 30, 2018 – 6:30 p.m.
Lake Nokomis Lutheran Church
5011 31st Ave South
Minneapolis, MN 55417
Meeting Presentation 

Community Meeting #4

Preconstruction Meeting

The Department of Public Works will hold an informational meeting to address questions about 34th Ave S reconstruction project. The meeting will be held on Tuesday, April 2, 2019. Below is the detail.

Tuesday, April 2, 2019
6:30 p.m.
Morris Park Recreation Center
5531 39th Ave S
Minneapolis MN 55417           

Business Meeting

Nokomis East Business Association and Nokomis East Neighborhood Association
McDonald's Liquors and Wine
Lower Level Event Room
5010 S. 34th Avenue South
Minneapolis, MN 55417 

March 13, 2017 – 4:00 p.m.

Project Updates

April 18, 2019 Update

See the full 34th Ave S project update from project engineer Menbere Wodajo.

March 8, 2019 Update

We plan tentatively to start construction on April 15, 2019.

June 4, 2018 Update

Pre-Assessment Meeting Presentation

May 1, 2018 Update

Newsletter Update

March 13, 2018 Update

Project is now planned for 2019. A Public Hearing is tentatively set for June 5, 2018.

March 24th, 2017 Update

The staff-recommended Project Layout (Part 1 and Part 2) was approved at the March 24th, 2017 City Council Transportation and Public Works Committee Meeting.

March 2, 2017 Update

The project's Preliminary Layout (Part 1 and Part 2) is now available.

Project Contacts

Menbere Wodajo, Construction Manager; [email protected] or 612-673-3716

Becca Hughes, Transportation Planner; [email protected] or 612-673-3594 

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.

Last updated Apr 19, 2019

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Salary Compliance Notice:
State statute 471.701; Notice of Salary Compliance, requires that the City post for not less than 90 days
the job title of the three highest paid employees along with their base salary. For 2018 these were:
1. City Attorney, $186,490
2. Assistant City Coordinator Convention Center, $183,600
3. Director Public Works, $181,191

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo