Public Works Logo

Public Works
350 South 5th Street
RM 203 City Hall
Minneapolis, MN  55415-1390

To contact, call 311.

28th Avenue South Bridge over Minnehaha Creek

In 2019 the City of Minneapolis will be reconstructing the 28th Ave S bridge crossing Minnehaha Creek in South Minneapolis.

2017-BR123-28th-Ave-S-Bridge-Rehab.gif

Project Status

CIP Status Stage 3: Preconstruction

Details

Project Limits

The bridge is located at 28th Ave S crossing Minnehaha Creek in the Nokomis-Hiawatha Regional Park in south Minneapolis. The project limits will extend to include the approach roadways north and south of the bridge.

Construction Schedule

Construction is anticipated to begin mid-June 2019, and be completed and open to traffic in late November of 2019.

Construction was initially scheduled to be undertaken in 2017, however, working within the Minnehaha Creek Watershed was required to obtain an Army Corps of Engineers permit. The process of obtaining the permit started in December 2015 and took longer than originally anticipated.

Traffic Impact

28th Avenue S traffic will be closed to all traffic modes during construction. See the project Detour Routes.

Documents

Project Layout

Detour Routes Map

28th Ave S Bridge Rendering

As part of the new design, a trail will cross under the reconstructed 28th Ave S bridge.

Updates

March 29, 2019: Bridge design is complete. Construction is anticipated to begin mid-June 2019 and be complete and open to traffic in late November of 2019.

Meetings

Two community meetings were held in May 2018 to get feedback from the community. Staff attended an October 2018 Standish Erickson Neighborhood Association Board meeting to share proposed railing options.

Railing Options - October 2018

Public Meeting - May 30, 2018
Presentation
Boards

Background

The existing bridge is a concrete arch bridge that was constructed in 1904. The arch has a clear span of 25 feet and rise of 7 feet. A multiuse Regional Park trail crosses 28th Avenue immediately north of the bridge on a skewed alignment. This trail is a component of the Grand Rounds National Scenic Byway which has been nominated for inclusion on the National Register of Historic Places.

When originally constructed, the bridge had a concrete railing and pedestrians & vehicles shared the roadway (see Figure 1). In the 1920s, sidewalks and metal railings were added. The sidewalks were cantilevered ~ 3.5 feet beyond the bridge spandrel walls. This provided the current ~4.5 foot sidewalks and moved pedestrians away from vehicular traffic (see Figure 2).

The primary purpose of the project is to provide a structurally-sound crossing over Minnehaha Creek for motorized and non-motorized users; and to provide a grade separated Grand Rounds trail crossing under 28th Avenue South for non-motorized users. The bridge will need to be reconstructed in order to accomplish this. The intent is also to continue to provide one vehicular traffic lane in each direction and wider sidewalks. The project will be developed after the community engagement process has been completed.

28th Ave S Figure 1.jpg28th Ave S Figure 2.jpg

Project Contact

Jack Yuzna, 612-673-2415 or [email protected]lismn.gov 

 

 (Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Apr 1, 2019

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Salary Compliance Notice:
State statute 471.701; Notice of Salary Compliance, requires that the City post for not less than 90 days
the job title of the three highest paid employees along with their base salary. For 2018 these were:
1. City Attorney, $186,490
2. Assistant City Coordinator Convention Center, $183,600
3. Director Public Works, $181,191

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo