Nicollet 2012

Nicollet Avenue Paving - Phase 1

Project Type:The proposed project is approximately 1 mile in length and is along Nicollet Avenue from Lake Street to 40th Street.  The street was originally constructed in 1954 and an asphalt overlay was done in 1977.  The proposed roadway will consist of two traffic lanes (one each way) and parking on both sides.  The project will include removal and replacement of the pavement, curb and gutter, driveways, sidewalks, and storm drain inlets.

Project Limits: The project is located in south Minneapolis on Nicollet Ave between Lake Street and 40th Street. Phase 1 will be constructed in 2012 between Lake Street and 36th Street. Phase 2 will be done in 2013 between 36th Street and 40th Street.

Construction Start Date: The proposed project is scheduled to start May, 2012.

Length of Construction:It is estimated the construction would be during the 2012 and 2013 construction seasons.

Traffic Impact:Unknown at this time

Meetings & Newsletters:

1-10-12 Meeting Notice

1-10-12 Meeting Agenda

1-10-12 Assessment Info

10-12-11 Open House Presentation

10-12-11_Meeting_Notice

9-23-11_Newsletter

8-16-11 Layout 3

7-12-11 Layout 2

7-12-11 Open House Presentation

7-12-11_Meeting_Notice

6-28-11_Newsletter

6-7-11 Layout 1

6-6-11 Open House Display Boards

6-6-11 Open House Presentation

6-6-11 Streetcar Handout

6-6-11 Streetcar Presentation

6-6-11_Meeting_Notice

6-2-11_Newsletter

 

Project Contact:  Beverly Warmka  612-673-3762

Project Updates:

Subscription E-mail Updates

 

May 11th Map Update

May 11th Update

May 4th Update

April 24th Update

April 20th Update

April 13th, Update

April 6th, Update

March 30th, 2012 Update

March 16th, 2012 Update

March 9th, 2012 Update

March 2nd, 2012 Update

 

Project Images:

Week of May 7th

 

March 29th, 2012:  Additional information regarding business assistance during road construction information can be found at: http://www.minneapolismn.gov/business/WCMS1P-089716

 

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated May. 11, 2012