33rd Ave SE & Talmage Ave

Project Type:
The proposed project will reconstruct 33rd Avenue Southeast between Como Avenue Southeast and Hennepin Avenue and Talmage Avenue between 29th Avenue Southeast and 33rd Avenue Southeast for a total length of 0.5 miles. The roads are currently constructed of oil-dirt and the adjacent properties are commercial. Both of these streets carry two-way traffic with parking on both sides. Additionally, a tremendous amount of patchwork has been done to this roadway in previous years. The existing road has little existing curb and gutter to aid drainage. The proposed plan will correct these problems and will add sidewalk, curb and gutter where they do not exist today.

These segments of 33rd Avenue Southeast and Talmage Avenue were constructed of oiled dirt and have never been constructed to current City standards. If the project is not constructed, the maintenance costs of the deteriorating roadway, which is past the point of preservation maintenance, will continue to increase.

 

Project Limits:

The project is located in southeast Minneapolis on 33rd Ave SE from Hennepin Ave E to Como Ave SE and Talmage Ave from 29th Ave SE to 33rd Ave SE.

Construction Start Date: 
Construction is complete.  Talmage will be seal coated in 2013, and sod will be placed along both Talmage and 33rd in 2013. 

Layouts & Photos:
Talmage 4-11-12
Talmage 5-9-12
Talmage 5-16-12
Talmage 5-23-12
Talmage 6-7-12
Talmage 6-13-12
33rd Ave SE 6-19-12
33rd Ave SE 6-28-12
33rd Ave SE 7-5-12
33rd Ave SE 7-11-12
33rd Ave SE 7-19-12
33rd Ave SE 7-26-12
33rd Ave SE 8-2-12
33rd Ave SE 8-8-12
33rd Ave SE 8-15-12
33rd Ave SE 8-22-12
33rd Ave SE 8-29-12
33rd Ave SE 9-5-12
33rd Ave SE 9-13-12
33rd Ave SE 9-20-12
33rd Ave SE 9-26-12

Contacts:  Tracy Lindgren  612-290-5898

Project Updates: 
Street paving and sidewalk work is complete.  Talmage will be seal coated in 2013, and sod will be placed along both Talmage and 33rd in 2013.

October 31, 2012: Update No. 32
October 25, 2012: Update No. 31
October 17, 2012: Update No. 30
October 11, 2012: Update No. 29
October 4th, 2012: Update No. 28
September 26, 2012: Update No. 27
September 20, 2012: Update No. 26
September 13, 2012: Update No.25
September 7, 2012: Update No.24
August 29, 2012: Update No. 23
August 22, 2012: Update No. 22
August 15, 2012: Update No. 21
August 9, 2012: Update No. 20
August 1, 2012: Update No. 19
July 25, 2012: Update No. 18
July 19, 2012: Update No. 17
July 11, 2012: Update  No. 16
July 6, 2012: Update No. 15
June 29, 2012:  Update No. 14
June 22, 2012:  Update No. 13
June 15, 2012: Update No. 12
June 11, 2012: Update No. 11
June 8, 2012: Update No.10
June 4, 2012: Update No. 9
May 24, 2012: Update No. 8
May 18, 2012: Update No. 7
May 9, 2012 Update No. 6
May 7, 2012: Update No. 5
April 27, 2012: Update No. 4
April 20, 2012: Update No. 3
April 12, 2012: Update No. 2
April 5, 2012: Update No. 1
March 28, 2012: Project Introduction

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

 