Pleasant St SE Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process. This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years. Without this program, streets in the in the program would not see surface improvements for many years.

Project Limits:
Pleasant St SE from Washington Ave SE north to match pavement just south of Arlington St.

Construction Start Date: 
August 1st, 2014

Duration of Construction:
Two weeks

Traffic Impact:
The road will be closed.

Contact: Chris Trembath 612-919-1196

Project Updates:
8-12-2014: The project is complete.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Aug 19, 2014