Nicollet Avenue Paving – Phase 2  

Project Type:
The proposed project is approximately 1 mile in length and is along Nicollet Avenue from Lake Street to 40th Street.  The street was originally constructed in 1954 and an asphalt overlay was done in 1977.  The proposed roadway will consist of two traffic lanes (one each way) and parking on both sides.  The project will include removal and replacement of the pavement, curb and gutter, driveways, sidewalks, and storm drain inlets.

Project Limits:
The project is located in south Minneapolis on Nicollet Ave between Lake Street and 40th Street. Phase 1 between Lake Street and 36th Street is now complete. Phase 2 will be done in 2013 between 36th Street and 40th Street.

Construction Start Date:
The proposed project is scheduled to start May, 2012.

Length of Construction:
Phase II will be completed in the 2013 construction season.

Traffic Impact:
Detour - July 11, 2013

Meetings:
March 26, 2013 Invite
March 26, 2013 Meeting Presentation

Project Update:

November 7, 2013:
There are a few things that still need to be completed (lighting, tree planting and minor clean-up), but most of the project is now complete.

October 30, 2013 Update
October 9, 2013 Update
September 26, 2013 Update
September 23, 2013 Update
September 18, 2013 Update
September 4, 2013 Update
August 21, 2013 Update

August 15, 2013 Update
August 6, 2013 Update
July 31, 2013 Update
July 24, 2013 Update
July 18, 2013 Update
July 11, 2013 Update
July 2, 2013 Update
June 27, 2013 Update
June 20, 2013 Update
June 13, 2013 Update
June 5, 2013 Update
May 29, 2013 Update
May 22, 2013 Update
May 15, 2013 Update
May 8, 2013 Update
April 30, 2013 Update
April 25, 2013 Update
April 23, 2013 Update
April 19, 2013 Update

January 30, 2013 Update
February 27, 2013 Update
March 6, 2013 Update

March 8, 2013 Update
March 18, 2013 Update

On-site Project Inspector: Bob Schmidt, 651-308-3805

 

Project Engineer: Beverly Warmka, 612-673-3762

 

Project Business Liaison: Erik Hansen, 612-673-5022

Link for Email Updates

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

 

Last updated Nov. 7, 2013