Page Residential Resurfacing
Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process. This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years. Without this program, streets in the in the program would not see surface improvements for many years.
Project Limits:
The Page Resurfacing Project is located in south Minneapolis bounded on the north by E Minnehaha Parkway, on the east by Chicago Ave, on the south by 54th St E and Diamond Lake Road, and on the west by 2nd Ave S. The Page area was originally paved 39 years ago in 1974.
Construction Start Date:
Construction is scheduled to begin tentatively the week of June 24th.
Length of Construction:
Not known at this time.
Traffic Impact:
The work will be performed during full or partial road closures. Please note that street parking will be impacted and short term intermittent access restrictions may occur. When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.
Paving Construction Survey:
Once the work is complete, please let us know how we've done. To do so, please access this website and take our Project Survey: https://www.surveymonkey.com/s/Page_Area. Or, you can simply call 311 and mention this project. We'd love to hear from you!
Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department. Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement. Full prepayments may be accepted only through December 31st, 2013 without interest. Partial prepayments are not provided for. No further notice of prepayment will be published. Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.
Contact: Chris Trembath 612-919-1196
Meetings:
Pre-Public Hearing: 6:30 PM, Thursday, March 7, Pearl Recreation Center, 414 E Diamond Lake Road
Formal Public Hearing: 9:45 AM, Tuesday, March 19, Council CHambers, City Hall, 350 South 5th Street, 3rd Floor
Project Updates:
Link to frequently asked questions.
Look for project updates here.
(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.
Last updated Jun. 12, 2013