E Minnehaha Parkway Paving

Project Type:
This is a Parkway Paving project. The existing asphalt roadway surface will be profiled and new asphalt will be placed on the roadway.

Project Limits:
The East Minnehaha Parkway Paving Project is located on East Minnehaha Parkway from Cedar Ave to 27th Ave S/ Woodlawn Ave. Due to necessary storm sewer work, the block between Cedar and Longfellow will be completed in 2014. 22nd Ave S, between Minnehaha Parkway and Nokomis Parkway will be included in this paving work in 2013.

Construction Start Date:
Resurfacing is scheduled to begin in September. Curb and gutter replacement will begin the week of Sept 2. The concrete crosswalks and manhole structures will be adjusted on September 16. Pavement removals are tentatively scheduled to begin on September 17th.

Length of Construction:
This work is being scheduled around the Minneapolis Bike Tour on September 15 and the Twin Cities Marathon on October 6. Curb and gutter replacement will be completed by Sept 13. On Monday, September 16, paving work will begin. The first day will involve preparatory work, and pavement removals are tentatively scheduled to begin on September 17. It is anticipated that all work will be completed by the Twin Cities Marathon. If for some reason something unforeseen arises, alternatives including weekend work and/or postponing certain work activities until after the marathon will be utilized.

Traffic Impact:
During the curb and gutter replacement, the parkway will be open to traffic. At times, traffic may be flagged to maintain through traffic.
During paving work, the construction activities will be performed under full road closure. Access to Nokomis Recreation Center will be maintained as much as possible, from either 28th Ave S or from Cedar. It is anticipated that there will be a couple of days that E Minnehaha Parkway will be completely closed while the final two layers of asphalt are placed. It is recommended that Nokomis Parkway be used for access during this time.

Bike paths will be open adjacent to the parkway. The concrete crosswalks are being removed. For safety’s sake, it is recommended that folks cross the parkway at 27th Ave S/Woodlawn Blvd or at Cedar.

Nokomis Recreation Center access:
During this work, we will try to maintain access as much as possible to Nokomis Recreation Center. The access will change over the duration of the project. It is anticipated during the first week of construction (week of Sept 16), the same route will be utilized all week. However, during the second and third weeks, it will vary over each week. Please check the Project Updates section at the bottom of this webpage for regular updates.

Nokomis Rec Center access map

Project Contact: Tracy Lindgren 612-290-5898

Project Updates:
10/01-13: Paving and the saw and seal is complete. Miscellaneous clean up work will take place during this week. The parkway is open to traffic.

9/23/13: Starting Wednesday, Sept 25, E Minnehaha Parkway will be completely closed and access to Nokomis Recreation Center will not be permitted from either direction. Please use the parking lot on Nokomis Parkway. There will also be a parking bay adjacent to the rec center that will be posted as a drop off location for the rec center. It is easiest to access this heading westbound on Nokomis Parkway (from the 28th Ave S side of the project). A link to Nokomis Rec Center access maps is found at the bottom of this webpage. This will be in effect for the rest of the week. All other traffic, please follow the detour. There will be no through traffic.

9/19/13: Starting Monday, Sept 23, access to Nokomis Recreation Center will be from Cedar Ave S. It is anticipated that Cedar will remain the access point a couple of days, and access will change mid-week. Signs will be posted at the access location. All other traffic, please follow the detour. There will be no through traffic.

Please check back early next week for an update for Nokomis Recreation Center access during week 2. It may be necessary to change the access route on short notice; please become familiar with the other access routes. We appreciate your patience and understanding during construction.

9/11/13: Starting Monday, Sept 16, access to Nokomis Recreation Center will be from 28th Ave S. It is anticipated that 28th Ave S will remain the access point for the first week of the project. Signs will be posted at the access location. All other traffic, please follow the detour. There will be no through traffic.

Nokomis Rec Center access map

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.