Public Works

350 South 5th Street
RM 203 City Hall
Minneapolis, MN  55415-1390

cooper location map

Cooper Residential Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process.  This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years.  Without this program, streets in the in the program would not see surface improvements for many years.

Project Limits:
The Cooper Resurfacing Project is bounded on the north by Lake St E, on the east by W River Parkway, on the south by 34th St E and on the west by 36th Ave S. The Cooper area was originally paved 31 years ago in 1982.

Construction Start Date:
Construction is scheduled to begin tentatively the week of May 20th.

Length of Construction:
Construction will last tentatively until the end of June, 2013.

Traffic Impact:
The work will be performed during full or partial road closures.  Please note that street parking will be impacted and short term intermittent access restrictions may occur.  When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department.  Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement.  Full prepayments may be accepted only through December 31st, 2013 without interest.  Partial prepayments are not provided for.  No further notice of prepayment will be published.  Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Contact:  Chris Trembath   612-919-1196

Meetings: 
Pre-Public Hearing: 6:30 PM, Wednesday, March 27, Longfellow Recreation Center, 3435 36th Ave S
Formal Public Hearing: 9:45 AM, Tuesday, April 2, Council Chambers, City Hall, 350 South 5th St, 3rd Floor


Project Updates: 
July 2, 2013:
This project is complete.  Crack sealing will take place in 2014.

May 28, 2013:
Construction began the week of May 20th and will probably last until the end of June.  We are resurfacing 42nd Ave South as well, although it is not shown on the map.  Please see this link for more information specifically regarding 42nd Avenue South.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.  

 

 

Last updated May 20, 2014

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

 

facebook25x25 twitter25x25 youtube25x25 Minneapolis311icon logo tv 14 footer icon image linkedin_32x32




mpls-logo-white120