46th Ave S Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process.  This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years.  Without this program, streets in the in the program would not see surface improvements for many years.

Project Limits:
The 46th Ave S resurfacing project is located in southeast Minneapolis on 46th Ave S between Lake St E and 38th St E.  This street was originally paved in 1982 or 1983 which is over 30 years ago. 

Construction Start Date:
Construction is scheduled to begin tentatively the week of June 24.

Length of Construction:
Not known at this time.

Traffic Impact:
The work will be performed during full or partial road closures.  Please note that street parking will be impacted and short term intermittent access restrictions may occur.  When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department.  Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement.  Full prepayments may be accepted only through December 31st, 2013 without interest.  Partial prepayments are not provided for.  No further notice of prepayment will be published.  Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Contact:  Chris Trembath 
  612-919-1196

Meetings: 
Pre-Public Hearing:
6:30 PM, Wednesday, March 27, Longfellow Recreation Center, 3435 36th Ave S
Formal Public Hearing: 9:45 AM, Tuesday, April 2, Council Chambers, City Hall, 350 South 5th St, 3rd Floor


Project Updates: 
June 27, 2013:  The project is complete.  Crack sealing will take place in 2014.
June 12, 2013:  Resurfacing is scheduled to begin tentatively the week of June 24th.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.


 

Last updated Apr 2, 2014