Public Works

350 South 5th Street
RM 203 City Hall
Minneapolis, MN  55415-1390

nawadaha location map

Nawadaha Blvd & Minnehaha Ave

Project Type:
The proposed project consists of full reconstruction of approximately 1,200 feet of roadway on Minnehaha Ave and Nawadaha Blvd.  This consists, at minimum, of full removal of the existing street surface, subgrade correction, aggregate base, paving, curb and gutter, signage and drive approaches, and pedestrian curb ramps.

Project Limits:
The proposed project consists of 950 feet of Minnehaha Ave from 46th St E, south to Nawadaha Blvd and approximately 250 feet of Nawadaha Blvd west from Minnehaha Ave.

Construction Start Date:
Currently scheduled for 2015.
 
The project is being coordinated with Hennepin County's reconstruction of Minnehaha Ave.
The Minnehaha Ave reconstruction is planned for 2015/2016. 


Hennepin County Minnehaha Construction Project
Minneapolis Minnehaha Construction Project

Length of Construction:
The project should be completed in the 2015 construction season between April-July.  It is being coordinated and constructed at the same time as the County's Minnehaha Ave - CSAH 48 reconstruction project. 

Traffic Impact:
Please expect traffic to be rerouted from the project limits.  Detour information is located on the County's project website and will be updated throughout the project.

Layouts, Detours & Images:
Minnehaha/Nawadaha Layout 9-26-13

Assessment Information:
Example Assessment Package
Areaway Notice Package

Public Meetings:
April 8, 2015 Meeting:
Public pre-construction information meeting: 5-7PM at Longfellow Recreation Center, 3435 36th Ave S, Minneapolis

January 13, 2015:
Pre-Assessment Public Meeting
5pm-6pm
Minnehaha Communion Lutheran Church
4101 37th Ave S,
Minneapolis, Mn 55406

January 20, 2015:
Public Hearing before City Council
9:45am,
City Hall, Minneapolis

City Project Contact: Chris Engelmann 612-673-3274
County Project Hotline: Number will be posted when activitated.
Assessments: Suzette Hjermstad 612-673-2401

Project Updates:
January 2015
September 23, 2013

July 8, 2013
 
(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.
 
 

 

Last updated Apr 6, 2015