31st St E Paving

Project Type:
This is a  paving project that will include removal and replacement of the pavement, curb and gutter, and driveway aprons.

Project Limits:
This project is located in south Minneapolis on 31st St E between Minnehaha Ave and 28th Ave S. 

Construction Start Date:
Currently scheduled to start the week of August 19, 2013. 

Length of Construction:
Substantial completion within 2.5 months.

Traffic Impact:
Closed to through traffic.  Local access will be maintained as much as possible.

Layouts, Detours, Images:
October 24th Meeting Invitation
October 24th Meeting
October 24th Meeting Notes

Project Contacts: 
Tracy Lindgren (City of Minneapolis) 612-290-5898
Harold Skjelbostad (BIKO) 612-991-3997 
 


Project Updates:
11-7-13:  The street is open to traffic and the sidewalk is installed.  Mpls Traffic will continue to work on street lighting.  In spring 2014, the boulevards w ill be sodded.

9-13-13:  Pavement removals, earthwork, storm sewer improvements, and grading are complete.  On Monday, September 16th, crews will start installing new curb and gutter, driveways and concrete pavement.  It is anticipated that this will take about two weeks, and cure time on the new concrete pavement will be required before it is open to traffic. 

Public Meeting on June 13, 2013

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.