West River Pkwy Paving

 Project Type:

This is a Parkway Paving project.  The existing asphalt roadway surface will be profiled and new asphalt will be placed on the roadway. 

Project Limits:
The West River Parkway Paving Project is located on West River Parkway from 22nd Ave S to 4th St S, and from the Frankin Ave ramps south to 26th St E.

Construction Start Date:

Construction is scheduled to begin on April 30th from the Franklin Ave ramps to 26th St E, and on May 1st for the section from 22nd Ave S to 4th St S.

 

Length of Construction:
The project will be completed in approximately one week.

 

Traffic Impact:
The work will be performed under full road closure.  There will be no parking on West River Parkway during the duration of the project.

 

Project Contact:  Chris Trembath  612-919-1196

 

Project Updates:
5/09/12:  The project is complete. 
Completed project photo.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

 

 

Last updated Apr 16, 2013

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

 

facebook25x25 twitter25x25 youtube25x25 Minneapolis311icon logo tv 14 footer icon image linkedin_32x32




mpls-logo-white120