Armatage Residential Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process.  This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years.  Without this program, streets in the in the program would not see surface improvements for many years.

Project Limits:
The Armatage Resurfacing Project is located in southwest Minneapolis between Xerxes Ave S and Penn Ave S, and between 54th St W and 58th St W.  The Armatage area was originally paved 30 years ago in 1982.

Construction Start Date:
The project is complete.

Length of Construction:
The project will be substantially complete in four weeks.

Traffic Impact:
The work will be performed during full or partial road closures this summer or fall.  Please note that street parking will be impacted and short term intermittent access restriction may occur.  When construction work will be done on a particular street in the project area, the street will be posted, NO PARKING, prior to work on that particular street.

Paving Construction Survey:
Once the work is complete, please let us know how we've done.  To do so, please access this website and take our Project Survey: http://www.zoomerang.com/Survey/WEB22GA5DB89YT or you can simply call 311 and mention this project.  We'd love to hear from you!

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department. Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement. Full prepayments may be accepted only through December 31, 2012 without interest. Partial prepayments are not provided for. No further notice of prepayment will be published. Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer’s Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612) 673-2401.

Contacts:  Tracy Lindgren  612-290-5898

Project Updates:
All paving is complete.  Next year, City crews will return for crack sealing.   

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

Last updated Apr. 16, 2013