38th Street East Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process.  This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years.  Without this program, streets in the in the program would not see surface improvements for many years.

Project Limits:
The 38th St E Resurfacing Project is located in south Minneapolis between Chicago Ave and 23rd Ave S, excluding the intersection at Cedar Ave.

Construction Start Date:
August 8, 2012: This project is complete.

Length of Construction:
The construction duration has not been determined at this time. Paving work on each road is expected to take several days. Scope and duration of coordinated utility improvements is yet to be determined.

Traffic Impact:
The work will be performed during full road closure. Detour Route

Note on Safe Routes Median Project at Bancroft:  
This project will coincide with the Safe Routes to School median project in front of Bancroft School.  However, that project is funded through a special Safe Routes funding source, and you will not be assessed for that project.

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department.  Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement.  Full prepayments may be accepted only through December 31, 2012 without interest.  Partial prepayments are not provided for.  No further notice of prepayment will be published.  Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the  Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Project Contact:  Chris Trembath   612-919-1196

Project Contact: (for Concrete Islands) Forrest Neil Hardy  612-221-8255

Project Updates:
August 8, 2012: This project is complete.
Pre-Public Hearing: 6:30 PM, Wednesday, My 23rd, Powderhorn Park Recreation Center, 3400 15th Ave S
Formal Public Hearing: 9:45 AM, Tuesday, June 5th, council Chambers, City Hall 350 South 5th St, 3rd Floor 

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Jan. 8, 2013