Penn Ave S Paving

Project Type:
The project will include removal and replacement of the pavement, curb and gutter, driveway aprons, storm drain inlets, and signal upgrades.

Project Limits:
The project is located in south Minneapolis on Penn Ave South between Minnesota Highway 62 and 50th St West. 

Construction Start Date:
April 15, 2013

Length of Construction:
2013 construction season

Traffic Impact:
The signed detour route will be Xerxes Ave via 50th St and the Crosstown.
Note: Penn Ave buses will be detoured to Xerxes Ave.  Bus 156 will not change.

Layouts, Detours, Images:

Penn Ave Construction Access 6-26-2013

Layout 1  Initial Concept
Layout 2  Initial Concept

Layout 3  Approved Layout

Assessment Area Diagram 
 

Meetings:
1st Public Meeting: January 10, 2012
Meeting Invitation
Meeting Agenda
Meetings Notes
Meeting Presentation
2nd Public Meeting: March 6, 2012
Meeting Invitation
Meeting Agenda
Meetings Notes
Meeting Presentation 
3rd Public Meeting: July 26, 2012
Meeting Invitation
Meeting Presentation
Meetings Notes 
4th Public Meeting: January 22, 2013
Meeting Invitation
5th Public Meeting: March 21, 2013
Meeting Invitation

Contact:
Stephanie Malmberg, Construction Engineer, 612-673-3365
Will Shutte, 612-673-3365
Chris Trembath, 612-919-1196
Bev Warmka, Design Engineer, 612-673-3762

GovDelivery Sign up for e-mail updates on this project.

Project Updates: 

11-7-2013 Update: Tasks remaining include installation of lighting, finish striping and punch list work.  Everything but the lighting should be complete by the end of next week.

10-18-2013 Update
9-13-2013 Update
9-10-2013 Update
8-21-2013 Update
8-15-2013 Update
7-26-2013 Update
7-16-2013 Update
6-28-2013 Update
6-21-2013 Update
6-13-2013 Update

6-06-2013 Update
6-03-2013 Update

5-17-2013 Update
5-09-2013 Update
5-03-2013 Update
4-17-2013 Update
4-12-2013 Update
4-05-2013 Update
2-21-2013 Update
8-06-2012 Update
4-13-2012 Update: City Council approved Layout 3.
3-28-2012 Update

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

 

 

Last updated Nov. 7, 2013