2018 Traffic Signal Upgrades

2018 Traffic Signals Webmap

Project Details

Project Description:
This project consists of upgrading the existing traffic signal systems to new American Disabilities Act (ADA) compliant pedestrian ramps with accessible pedestrian signals (APS), countdown pedestrian timers, and overhead mast arm signals.

Project Locations:
The following six signals will begin construction on April 30, 2018. Signals will remain operational with a temporary system during construction. Pedestrian access will be maintained during construction. The duration is approximately 10 weeks. 

Construction Start Date:
2018 Construction Season

Duration of Construction:
Each signal will be turned off for approximately 8 weeks during construction except at locations where temporary traffic signals have been installed.

Project Contact

Ryan Anderson, P.E., Traffic Engineer, 612 673-3986 or [email protected]

 

Last updated Apr 20, 2018