Nokomis Neighborhood Area Resurfacing

Nokomis Area Resurfacing Webmap

Project Status

CIP Status Stage 4: Construction

Project Description

Summary of Work
Resurfacing the streets in the Nokomis neighborhood area; repairing miscellaneous concrete structures

Schedule
Start date is April 5, 2018.

Location
34th Avenue South to 40th Avenue South; 54th Street East to East Minnehaha Parkway

Benefits
Resurfacing will improve deteriorating driving surface and extend pavement life until a more comprehensive project can be undertaken.

Traffic Impact
Intermittent street closures as posted

 

Project Contact

Chris Trembath; 612-919-1196 or [email protected]

 

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Apr 13, 2018