TR022 - 2017 Traffic Safety Improvements
Project Details
Project Description:
This project consists of upgrading the existing traffic signal systems to new American Disabilities Act (ADA) compliant pedestrian ramps with accessible pedestrian signals (APS), countdown pedestrian timers, and overhead mast arm signals.
Construction Start Date:
March 2017
Duration of Construction:
Each signal will be turned off for approximately 8 weeks during construction except at locations where temporary traffic signals have been installed.
Project Sites:
35th & Park, 35th & Portland, 36th & Park, 36th & Portland
- Work is completed
35th at Blaisdell, 1st, 3rd, and 4th Ave
- Work is completed
36th at Blaisdell, 1st, 3rd, and 4th Ave
Work is completed
24th at Park, Portland, Chicago, 11th, Bloomington & 19th Ave
- Work is Completed
50th & Minnehaha, 50th & James, 50th & Vincent Ave, 54th & Garfield Ave
- Construction begins 6/19
Penn & 34th, Emerson & Dowling, 4th St. & 4th Ave, Como 8 18th Ave
-Construction begins 6/19
34th & Grand, 26th & 10th, 42nd & 42nd
- Construction Begins 7/31
24th at Hennepin, Dupont, Lyndale. Blaisdell, Nicollet, 1st, 3rd
- Construction Begins 8/23
Project Contact
Contact: Ryan Anderson, P.E., Traffic Engineer, 612 673-3986 or [email protected]
Last updated Dec 13, 2017