18th Avenue NE (Monroe to Johnson) Reconstruction

 18th-Ave-NE-Web-Map-updated-12-13-17

Project Status

CIP Status Stage 4: Construction

Project Details

Project Type:
Reconstruction

The project will include full removal of the existing street, subgrade correction, new pavement, curb and gutter, driveways, bike trail, sidewalk as needed, streetscape elements as needed, and utility work as needed. The reconstruction will impact local access, parking and pedestrian paths.

Project Limits:
The project is located in northeast Minneapolis. The limits of 18th Avenue NE are from Monroe Street NE to Johnson St NE.

Project Information:

18th Avenue NE Concept Layout 
First Public Informational Meeting 
First Public Informational Meeting Presentation 
Second Public Informational Meeting 
Second Public Informational Meeting Presentation 

Construction Start Date:
Construction began in June 2017.

Duration of Construction: 
The majority of work was completed in 2017. The contractor will continue work on the remaining items beginning in May 2018. These items include completing the signal work at Monroe Street Northeast and Johnson Street Northeast, raising the manholes to the final surface elevation, completing the sidewalks and driveways, and the installation of the shared-use trail on the south side.

Traffic Impact:
To be determined; however, portions of 18th Avenue Northeast between Monroe Street Northeast and Johnson Street Northeast will be closed to through-traffic.  

road5     road2.png

Construction August 23, 2017.

Meetings

Preconstruction Meeting
June 1, 2017
Yinghua Academy
1616 Buchanan St NE
Meeting Invitation Letter
Meeting Presentation

Assessment Meeting
January 10, 2017
Parker Skyview highrise, Community Room
1815 Central Avenue Northeast
Meeting Invitation Letter
Meeting Presentation
 

Project Updates

April 12, 2018 Update

December 1, 2017 Update

November 20, 2017 Update

November 7, 2017 Update

October 31, 2017 Update

October 30, 2017 Update

October 19, 2017 Update

October 16, 2017 Update

October 13, 2017 Update

October 11, 2017 Update

October 6, 2017 Update

September 29, 2017 Update

September 22, 2017 Update

September 20, 2017 Update

September 18, 2017 Update

September 8, 2017 Update

September 1, 2017 Update

August 25, 2017 Update

August 17, 2017 Update

August 11, 2017 Update

August 4, 2017 Update

July 28, 2017 Update

July 20, 2017 Update

July 14, 2017 Update

July 7, 2017 Update

June 30, 2017 Update

June 20, 2017 Update 

 

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.

 

Contact: Beverly Warmka, 612-673-3762
 

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

Last updated May 16, 2018

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Minneapolis 14 Government TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo