38th Street East Resurfacing

2017-PV056-38th-St-E-webmap-2-6-17.gif

Project Status

CIP Status Stage 5: Complete

Project Details

Project Type:
Resurfacing

Project Location:
38th Street East from Minnehaha Avenue to West River Parkway

Construction Dates:
Milling of pavement will be done on Aug 10th, 2017

Paving scheduled to take place between Minnehaha Avenue and 41st Avenue on August 11, 2017

Paving scheduled to take place between 41st Avenue and Edmund Blvd August 14th

Schedule subject to change due to weather and other circumstances

 

Meetings

Pre-Public Hearing
6:30 p.m., Wednesday, March 8, 2017
Sibley Recreation Center, 1900 E 40th Street 

Formal Public Hearing
9:30 a.m., Tuesday, March 14, 2017
Council Chambers, City Hall
350 South 5th Street, 3rd Floor

Project Updates

August 14, 2017: Project is complete.

 

Contact: Chris Trembath, 612-919-1196 or chris.trembath@minneapolismn.gov

 

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

Last updated Aug 23, 2017

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

 

facebook25x25 twitter25x25 youtube25x25 Minneapolis311icon logo tv 14 footer icon image linkedin_32x32




mpls-logo-white120