Warrington Area/4th Ave S Resurfacing

Warrington-Area-webmap-4-26-17.gif

Project Details

Project Type:
Resurfacing

Project Location: 
Warrington area/4th Ave S

Construction Start Date:
Project work is complete. There are 4 areas that are on hold until underground utility issues are resolved. 3 of 4 blocks of this project that were on hold due to voids under pavement will be resurfaced in May 2017.

The 3900 block of 5th Avenue South is scheduled for Milling and Paving the week of May 15, 2017.

Duration of Construction:
The project is complete. There are 3 areas that are on hold until underground utility issues are resolved.
The sections of 41st Street East from Columbus Avenue to Chicago Avenue, and 39th Street East from Portland to Oakland were both resurfaced on November 3, 2016 after being on hold for sewer work.

Traffic Impact:
Street closures, temporary parking restrictions.

Detour Maps for 4th Street Resurfacing:
Lake Street to 34th Street Detour
33rd Street to 36th Street Detour

Public Meetings:

Pre-Public Hearing:
6:30 PM, Wednesday, March 30
Sabathani Community Center
310 E 38th St

Formal Public Hearing:
9:30 AM, Tuesday, April 5
Council Chambers, City Hall
350 South 5th Street, 3rd Floor
 

Project Updates

Last updated May 15, 2017

Updated April 26, 2017

Updated April 3, 2017

Updated November 4, 2016

Updated October 19, 2016

Updated October 4, 2016

Updated September 2, 2016

August 17, 2016: Asphalt mill and overlay work will start on the project on August 25, 2016 and will continue until the project is complete.

August 10, 2016: Miscellaneous concrete work on the project has been completed as of July 20, 2016. Asphalt resurfacing work will start mid-August on the streets near Richard E Green Central Park Elementary School and the Bryant Jr. High School. City crews will resurface the rest of the streets in the project when the gas company completes their work. All work on the project is expected to be completed in 2016, except the area described in the August 1 update below.

August 1, 2016: A section of the Warrington area resurfacing will be postponed until 2017, to coordinate with planned sewer work.
Resident Letter about Postponed Section

Updated June 29, 2016

 

Main Contact: Chris Trembath, 612-919-1196
Sewer Project Contact: Will Shutte, 612-673-3606

 

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated May 15, 2017

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

 

facebook25x25 twitter25x25 youtube25x25 Minneapolis311icon logo tv 14 footer icon image linkedin_32x32




mpls-logo-white120