Penn, Penn East, McKinley, Humboldt & Girard Resurfacing

Project Type:
Resurface asphalt driving surface. Penn East was originally paved in 1978.  McKinley was originally paved in 1981.  Girard and Humboldt Aves N were originally paved in 1969 & 1978.

Project Limits:
The project is located in north Minneapolis and is mostly bounded on the north by Dowling Ave, on the east by Lyndale Ave N, on the south by Lowry Ave and on the west by Penn Ave N.  Humboldt and Girard extend south to 26th.

Construction Start Date:
Project was completed on August 3.

Duration of Construction:
The duration of the project in front of a home or business will be about two days.  These days may or may not be consecutive.  The overall project area will take about eight weeks to complete.

Traffic Impact:
Short term coordinated road closures, sudden stops and flaggers may be controlling traffic.

Meetings:

Pre-Public Hearing:
6:30 PM, Tuesday, February 10, Folwell Recreation Center, 1615 Dowling Ave N
Formal Public Hearing:
9:30 AM, Tuesday, February 17, Council Chambers, City Hall, 350 South 5th Street, 3rd Floor

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department. Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement. Full prepayments may be accepted only through December 31st, 2015 without interest. Partial prepayments are not provided for. No further notice of prepayment will be published. Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Contact: Chris Trembath 612-919-1196

Project Updates:

November 3, 2015: Project is completed.

Updated August 4, 2015

Updated July 21, 2015

May 19, 2015: Milling is finished and paving has started from east to west.  Asphalt will be completed on 5/21 on McKinley.  Asphalt paving is proceeding west across Penn East and then Penn.  These projects should be completed by late June.

April 30, 2015:
Curb & gutter replacement on these projects is complete. Asphalt resurfacing started the week of April 20th on the McKinley Project and will proceed westward across the Penn East and Penn projects. Private utility work is being done in the area ahead of the resurfacing project.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Jan 22, 2016

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 