Lyn Park Residential Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process. This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years. Without this program, streets in the in the program would not see surface improvements for many years.
The Lyn Park Residential Project consists of three previous residential projects; Lyn Park 2 originally paved in 1978, Lyn Park 3, and Franklin Hall N, originally paved in 1976.

Project Limits: 
The project is located in north Minneapolis and is bounded on the north by West Broadway, on the east by I-94, on the south by Plymouth Ave and on the west by Bryant Ave S.

Construction Start Date:
Mill and overlay work begins the week of June 30th.  Select curb and gutter replacement will take place prior to the mill and overlay.

Duration of Construction:
Construction will take about 3-4 weeks for completion, barring  unforeseen circumstances.

Traffic Impact:
The work will be performed during full or partial road closures. Please note that street parking will be impacted and short term intermittent access restrictions may occur. When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.

Meetings:
Pre-Public Hearing:
6:30 PM, Tuesday, April 22, North Commons Recreation Center, 1801 James Ave N
Formal Public Hearing:

9:30 AM, Tuesday, May 13, Council Chambers, City Hall, 350 South 5th Street, 3rd Floor

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department. Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement. Full prepayments may be accepted only through December 31st, 2014 without interest. Partial prepayments are not provided for. No further notice of prepayment will be published. Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Contact: Chris Trembath 612-919-1196

Project Updates:
07-21-14:  This project is complete.  Crack sealing will take place in 2015.
07-01-14:  Milling began June 30 and is in progress.  Paving to begin early next week.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Mar 31, 2016

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

CONNECT

311 call center

TTY relay service

 

facebook25x25 twitter25x25 youtube25x25 Minneapolis311icon logo tv 14 footer icon image linkedin_32x32




mpls-logo-white120