Chicago Avenue
Project Type
On-street bike lanes
Project Limits
Chicago Avenue – 49th Street E to 60th Street E
Construction Start Date
2011
Contact Information
Shaun Murphy, (612) 333-2450 or shaun.murphy@minneapolismn.gov. Feedback can also be entered using our online form.
Project Details
Lane changes will include bike lanes in each direction on every block of the project.
Striping will be in paint.
No parking changes will take place.
Project Updates
June 22, 2011
The plan to add bike lanes has been shared with neighborhood groups and at an open house for the related resurfacing project. Striping will occur subsequent to the 2011 mill and overlay, which has not yet been scheduled.
Other Information
This bike lane project is part of Public Works efforts to take advantage of existing resurfacing and seal coating projects, and is funded through the regular Public Works operating budget.