E 54th St Bike Accomodations

Project Details

Bike Facilities will be introduced on E. 54th St. between Lake Nokomis Parkway and Portland Ave. late summer 2013.

Possible Facility Types:

Advisory Bike Lanes
 
Bike Lanes
 
Shared Lane Markings
 

Project Limits:

E. 54th St. between W. Lake Nakomis Pkwy and Portland Ave. S

Project Area Map

Project Schedule:

July

7/12/13: City Crews finish resurfacing

7/15/13-7/26/13: Community Input window

7/25/13: Public Meeting, Hale School. 6pm. All are welcome.

7/31/13: Deadline for community input to choose facility type

August

8/1/13-8/9/13: Finalize Plans, Submit for approval

Week of 8/12/13 (Tenative): Restriping and implementation of facilities


Contact Information

Project Manager: Michael Zenker, 612-240-7592 or michael.zenker@minneapolismn.gov. Feedback can also be entered using our online form.

 

 

Last updated Jul. 12, 2013